Current Projects

Council District 1

The area generally north of 23rd St. and west of Noland Rd.

ProjectStatus
Filter Painting
Courtney Bend Water Plant
Project Complete
PLC Upgrade
Courtney Bend Water Plant
IN PROCESS
Settling Basin Painting
Courtney Bend Water Plant
25% completed

Council District 2

The area generally north of 23rd St. and Truman Rd. and east of Noland Rd.

ProjectStatus
12" D.I. Water main on Truman Rd.
From Yuma to Alexander
Design is being reviewed.
Little Blue Parkway-Phase 10 Ditch Repair over 36" D.I. Water Main
Little Blue Parkway
Bids were opened on August 11th, 2016 and the low bidder was Triple C Underground. 1st Reading to award contract will be Sept.6, 2016.

Council District 3

The area generally south of Truman Rd. and 23rd St. and east of Lee's Summit Rd., also the area bordered by Noland and Lee's Summit Roads and 23rd and 35th Streets.

ProjectStatus
12" D.I. Water Main on 23rd St.
From West of Hub Dr. to West of Trail Ridge
Design Stage

Council District 4

The area generally south of 23rd St. and west of Noland Rd., also the area bordered by Noland and Lee's Summit Roads and 35th St. and 40 Hwy.

ProjectStatus
16” D.I. WATER MAIN ON NORTHERN BLVD.
FROM 28th STREET TO HARRIS AVE.
Pyramid Excavation will begin work August 29th and has till May 24th, 2017 to complete. Any questions concerning construction should be directed to Scott Howell at 325-7650.