2014 Asphalt Overlay Project



Project Name: 2014 Asphalt Overlay Project
Location: City-wide

Description:

This contract provides for, but is not limited to, pavement cold milling, asphalt concrete overlay, wedging and patching, Portland cement concrete handicap ramps, thermoplastic pavement striping, traffic control, and all appurtenant work. (Project No. 70111401)

Update: This project is currently 55% complete.

Start Date: August 11, 2014
Contractor: Superior Bowen
Contact Person: Shar Dilmaghani, 325-7611


Last Report Date: 11/10/14
Project Status: Construction