Skip Navigation

Rock Creek Interceptor Improvements Segment 10A



Project Name: Rock Creek Interceptor Improvements Segment 10A
Location: N. Sterling Ave. to N. Forest Ave.

Description:
This project provides for, but is not limited to, construction of approximately 3,300 LF of 8 IN through 30 IN gravity sewer pipe, manholes, concrete encasement, creek crossings, bypass pumping, asphalt replacement, and all other appurtenances.

Invitation to bid
Bid Tabs

Start Date: Aug. 19, 2014
Contractor: VF Anderson
Contact Person: Jennifer Gaffney, HDR Engineering 816 347-1140



Last Report Date: 9/9/14
Project Status: Construction

Privacy Policy
© 2014 City of Independence, Missouri. All rights reserved.