Water Department

12" D.I. Water main on Truman Rd.

Project Name: 12" D.I. Water main on Truman Rd.
Location: From Yuma to Alexander

Description:

Installation of approx. 4,680 ft. of 12 in. d.i. class 52 pipe and materials. Bid was awarded to Westland Construction. Construction began on April 3rd and Westland Construction has until Dec. 29, 2017 to complete. Any questions concerning construction should be directed to Scott Howell at (816) 325-7650.


Last Report Date:
Project Status: This project is currently under construction by Westland Construction. Westland Construction has until December 29, 2017 to complete project. Any questions concerning construction should be directed to Scott Howell at (816)325-7650.