Water Department

Council District 3

ProjectStatus
12" D.I. Water Main on 23rd St.
From West of Hub Dr. to West of Trail Ridge
The Water Main portion of this project has been completed by Blue Nile Contractors. There is still some sodding and final grading to complete. Contractor has until July 12, 2018 to complete.
12" DI Water Main
On 23rd St. from West of Trail Ridge to Haden
This project is currently in the design stage. Any questions should be addressed to Scott Howell in Engineering at 816-325-7650.
6" D.I. Water Main on Queen Ridge and Ellison Way
on Queen Ridge and Ellison Way, South of 23rd Street
This project is currently in the design stage. Any questions should be directed to Scott Howell at (816)325-7650.