Project Name: 39th Street Bridge
Location: Over the Little Blue River

Description:

This contract provides for, but is not limited to, the necessary grading, paving, bridges, culverts, storm sewer improvements, concrete curb and gutter, driveways, concrete sidewalks, concrete bike path, seeding, signing, pavement marking and all appurtenant work for the completion of the project. (City Project No. 70511103) and Federal Project Number BRM -3379 (430).

Update:  The Notice to Proceed has been issued.  The contractor is to build a new bridge next to the existing bridge and then switch traffic to maintain traffic during construction.

View Invitation to Bid.
View plan holders list.
View bid tabs.         

Update: This project is under construction and is 52% complete. 

Start Date: Oct. 23, 2013
Duration: 360 days
Contractor: Phillips Grading
Contact Person: 
Shar Dilmaghani, 325-7611
    


Last Report Date: 8/14/14
Project Status: Construction