Project Name: 35th Street Improvements
Location: 35th Street, Crysler to west of Noland

Description:

This contract provides for, but is not limited to, the necessary grading, asphalt & concrete paving, culverts, storm sewer improvements, concrete curb and gutter, driveways, concrete sidewalks, sodding, signing, pavement marking, retaining walls, and all appurtenant work for the completion of the project. (City Project No. 70110804) and Federal Project Number STP 3379 (425).

Update: The project is 100% complete.

View Invitation to Bid.
View plan holders list.
Addendum 1.
View bid tabs.

Start Date: April 29, 2013
Duration: 270 days
Contractor: VF Anderson
Contact Person: 
Shar Dilmaghani, 325-7611


Last Report Date:
Project Status: Complete