Skip Navigation

Little Blue Parkway, Phase 10 (24 Highway)



Project Name: Little Blue Parkway, Phase 10 (24 Highway)
Location: 24 Highway west of Powell Road

Description:

This contract provides for, but is not limited to, the necessary grading, paving, culverts, storm sewer improvements, concrete curb and gutter, driveways, concrete sidewalks, asphaltic concrete multiuse pathways, seeding, signing, pavement marking, traffic signals, retaining walls, and all appurtenant work for the completion of the project. (City Project No. 70510802) and Federal Project Number DP 3379 (421).

Update: This project is 100% complete.

View Invitation to Bid.
View plan holders list.
View bid tabs.



Start date: July 5, 2012
Duration: 210 days
Contractor: VF Anderson Builders, LLC
Contact Person: Shar Dilmaghani, 325-7611 


Last Report Date:
Project Status: Construction